LSO visited under constructed protective wall in Kuchdeh on July 27 2011. 90 percent work is completed.
Protective wall of length 41ft is completed while another part of length 134 ft is at the last stage of completion. Labours are working with efficiency while project committee monitoring them on regular bases.
Mr. Aain Ali Shah member project committee said that thy have received the second release till now we have almost completed our project. I have submitted the expenditure statements to the AKRSP Ghkuch but still third release is not paid which creates disappointment in skilled and unskilled labours. He requested to pay them third release immediately.