AUDIT REPORT OF WOMEN ORGANIZATION CHATORKHAND PAIN II.


Village Accountant Mrs. Zar Bibi carried out the audit of Women Organization Chatorkhand Pain II.  
This report was presented by LSO on Mrch 10, 2011.
The summery of report is given below:

Total Savings

6,23,260
In Bank (PLS)
1,17,444

Loan to members
4,97,817

Audit Fees
500

Stationery Exp.
450

Cash in hand
7049

Total
6,23,260


There are 66 members in this W/O. 45% members accessed the loan during this year. The recovery system of loan is not too satisfactory therefore Manager and President of W/O are advised to review the recovery method and take necessary steps to ensure the recovery n time.
Recordkeeping is good but need more work on it for better performance of W/O.

Few clips are as following: 
child member of W/O Shehla Gul reciting from the Holy Quran on the begining of meeting
r. Muhammad Saleem Manager LSO shareing his ideas about aduit and its benefits
President and Manager of W/O during the meeting
Members are listenng to there report during the meeting.
Miss Salima Community Mobilizer presenting the Audit Report.

Thursday 17 March 2011

Follow up of Protective Walls and Link Road Village Organization Kuchdeh

A project of Protective Walls in the flooding stream between Kuchdeh and Birgal is being under construction. This project given to V/O Kuchdeh by the AKRSP and Focus Pakistan. The division of walls between Kuvhdeh and Birgal Valley are shown in the table.

Name of NGO Kuchdeh Side Birgal Side
AKRSP 200 ft 200 ft
Focus 250 ft 150 ft
135 ft


Another project of reconstructing damaged Link Road also under construction. It length is 12 x 1500 ft from Power Station to upwards.

A Power Station and almost 130 Households will be protected after constructing these walls on Kuchdeh side. While million Kanaals of cultivated land and plants will be safe as well.

LSO Chatorkhand visited the sites on March 15, 2011 and observed work on progress.
Few clips of work in progress are as following on both projects:

Work in progress on Link Road Kuchdeh

Digging for constructing protective walls of 200 ft and 135 ft length.

Labours are collecting stones for walls

Power Station Chatorkhand

Clip of Power Station which was luckily
remained safe during floods of July 2010.

Kuchdeh Project

Labours are working on the site while
Mr. Aain Ali Shah member project
committee monitoring them.

Wednesday 16 March 2011

Meeting with wo Dain Pain 1 and Kiran Educated

An important meeting with Women Organization Dain Pain 1 and Kiran Educated Dain was held Feb. 10, 2011 in the lawn of Pain Jamatkhana Dain. Both w/os were merged into each other and needs to separate each other.

Meeting was formally begun with the name of Almighty Allah. Mrs. Tajreen recited few verses from the Holy Quran.

Manager LSO Mrs. M. Saleem briefed the members about LSO and its responsibilities. He highlighted the issue of members participations in both w/os and explain them the drawbacks of current situation of their w/os. He said that that was against the rule and regulations of AKRSP and LSO.
Manager gave them two suggestions to completely separate them or form one w/o.

After that all the members were agreed to separate w/o and decided to join the w/o of their nearest one.
Miss Malika manager W/O Dain Pain 1 was ordered to go back to her own area “Chatormari” with her members and Miss Amina Manger W/O “Kiran Educated” will stay in her current area.

Both the managers said that many members borrowed money from them and we need time to recover of the loans. Secondly thy have deposited their savings in banks and maturity of their deposits will complete in the month of April 2011.


Mrs. Tajreen reciting verses
From the Holy Quran


Member of W/O listening to the manager during meeting.

Manager explaining the issue and its demerits of the member 


who takes part in two or three W/Os at a time.