Follow up of Protective Wall Village Organization Shunas

A project of Protective Wall on the sides of flooding stream donated by KFW is being in progress in Shunas Valley. Total length of this wall is 250 ft and 8ft high.
This wall is divided into three parts in ratio of 100 ft : 75ft : 75 ft. First part (100ft) is constructed up to 6ft. 85% work is completed on this wall.
Digging for the Wall of 75ft length is completed and another 75ft is remains untouched while all the materials e.g stones, gravel and sand are collected on the site.
Mr. Nadir Shah Project Committee member said that work was stopped due to timely not payment of second release from the AKRSP. He said that all the expenditure statements of Rs. 67000/- (First release) are already submitted to the Area Office Gahkuch but there is no any response from them in this regards.  He hoped that construction will restart soon after on releasing second payment.     



Work in progress on the site (100ft)

Digging on 75ft wall is ready for construction

Sand, gravel and stones are collected on the site.

Mr. Nadir Shah member Project Committee
briefing about construction.